Construction Progress
July 2024 - Building B: Last Remaning Building Available Now!
December 2023 - Building A & B: Available Now!
October 2023 - Building A: Available Now & Building B: Delivering Q4 2023
September 2023 - Building A: Available Now & Building B: Roof Complete
August 2023 - Building A: Available Now & Building B: Roof Nearing Completion
July 2023 - Building A: Available Now & Building B: Roof Underway
June 2023 - Building A: Available Now & Building B: Roof Underway
May 2023 - Building A: Complete & Building B: Walls Tilted
April 2023 - Building A (±637,868 SF): COMPLETED!
April 2023 - Building A: Nearing Completion & Building B: Slab Pour Underway
March 2023 - Building A: Nearing Completion & Building B: Slab Pour Underway
March 2023 - Building A: Delivering Q1 2023 & Building B: Slab Pour Nearing Halfway
February 2023 - Building A: Delivering Q1 2023 & Building B: Slab Pour Underway
January 2023 - Building A: Roof Complete & Building B: Footers Poured
January 2023 - Building A: Roof Nearly Complete
December 2022 - Building A: Roof Halfway Complete
December 2022 - Building A: Roof Underway
November 2022 - Building A & B
Building A (Front): Walls Complete. Building B (Back): Pad Ready
November 2022 - Building A: Walls tilted
October 2022 - Building A: Slab completed
October 2022 - Building A & B
Building A (Below): Slab Pour Nearly Complete. Building B (Above): Site Prep Complete
August 2022 - Building A: Slab pour underway
August 2022 - Building A & B
Footing being poured for Building A (right). Site prep on Building B (left).